Unbelievable but true that the much talked subject around the replacement of the sewage pipeline in the Plano area is now something of the past, and also the cause of particular concern and anxiety is whether and how it will work and will it respond to the summer needs of the wider region.
The new pipeline was placed in a very short time to a distance of about 700 meters after the necessary approvals and licensing. Soon the rehabilitation of the provincial road is expected, according to the permit provided by the vice-Regional offices, but also considering that the road where the excavations were made is the central road of Planos, which will soon receive a very high volume of traffic.
Increase in capacity
It is reminded that the activation of the processes that has to do with the extension of the Biological Cleaning facilities was taken by the Board of Directors of the Zakynthian Water board (DEYAZ). It was invited to approve the modification of the study on “Expansion and Upgrading of the waste treatment plant (Ε.Λ.Λ), as well as the Environmental Impact Assessment of Biological Cleaning (AEΠΟ amendment), in order to increase plant capacity from 50% initially and projected to 150%. This will not only serve the drainage networks that are being planned such as the drainage of Tragaki and Kypseli, but also the existing Planos works, which have already begun interventions for the replacement of the pipeline and has been completed to a large extent.
Also, the approval of the direct assignment for the design of a mapping study of the existing Planos Network. The usefulness of mapping the network is to know its strengths and capacity, but also the problems it presents, is a one-way street to correct the mistakes of the past, and finally to join and legally the waterboard’s network at last.
A wish
It is a wish of everyone to proceed and stop patching up the acute and serious problem of the Planos Sanitation System for it to be replaced under mechanical support to ensure a proper working network
However, a prerequisite, when it comes to infrastructure of general interest, is to do as much as possible with the statutory procedures. All this for a project which had started in 2002 and with the initiative of private businesses in the area of Planos involved in tourism, was completed within 40 days, It did not cost the state a single euro and was donated to the then Municipality of Arcadia.